The Carolina Crossroads project is SCDOT’s $2.69 billion rebuild of the I-20, I-26, and I-126 interchange in Columbia, commonly known as “malfunction junction.” SCDOT’s project site lists 132 new lane miles and 43 new bridges, and it expects substantial completion in the mid-2030s.
Quick facts
| Item | Detail | Date | Source |
|---|---|---|---|
| Program cost | $2.69 billion investment | Project site | SCDOT project site |
| New lane miles | 132 new lane miles | Project site | SCDOT project site |
| Widened interstate | 14 widened interstate miles | Project site | SCDOT project site |
| Bridges and interchanges | 43 new bridges and seven reconstructed interchanges | Project site | SCDOT project site |
| Construction start | Construction began in November 2021 | Project site | SCDOT project site |
| Re-phasing | Announced in February 2024 | February 2024; opened Oct 5, 2026 | SCDOT About |
| Substantial completion | Expected in the mid-2030s | Project site | SCDOT project site |
Background
Carolina Crossroads is SCDOT’s program to rebuild the interchange where I-20, I-26, and I-126 meet in Columbia. SCDOT’s project site says construction began in November 2021 and is organized into phases. SCDOT’s About page says that in February 2024, “it was announced that upcoming phases of construction would advance the widening of I-20.” Phase 3 was divided into subphases A through E, and Phases 4 and 5 were combined.
Timeline
- November 2021: Construction began (SCDOT project site).
- February 2024: SCDOT announced the re-phasing of upcoming construction phases (SCDOT About).
- Mid-2030s: Substantial completion expected, as of October 5, 2026 (SCDOT project site).
What it means for relocating businesses
SCDOT already re-phased this project once, in February 2024, after construction had already started in 2021. That matters more than the mid-2030s completion date by itself: it shows a published schedule here has already gone stale once before, so an older plan or a secondhand summary of the project may not match what SCDOT is actually building toward now. Check the project’s own site for the current phase, not a figure from a 2021 or 2023 article.
A business that leases this year would operate alongside most of the construction window, since substantial completion isn’t expected until the mid-2030s. Ask your broker or landlord which road access the site will use during that period, since the work is staged by phase, not finished on one date.
Questions people ask
What is “malfunction junction”? SCDOT’s project site says the I-20, I-26, and I-126 interchange is “commonly known as ‘malfunction junction.'”
When is the project expected to finish? SCDOT’s project site expects substantial completion in the mid-2030s.
How large is the program? SCDOT lists a $2.69 billion investment, 132 new lane miles, 14 widened interstate miles, 43 new bridges, and seven reconstructed interchanges.
Has the schedule changed? Yes. SCDOT announced a re-phasing in February 2024, so check the project site for current phase dates.
Sources
- SCDOT, Carolina Crossroads project site, undated. Opened October 5, 2026: scdotcarolinacrossroads.com
- SCDOT, Carolina Crossroads About page, undated. Opened October 5, 2026: scdotcarolinacrossroads.com/about
Last updated October 5, 2026.