In 1925, Charleston Harbor’s tide gauge recorded no flood events above the minor-flood line. In 2023 it recorded 75. The U.S. Army Corps of Engineers is now designing a coastal storm plan for the peninsula, with early construction slated for 2027 to 2031, if the money comes through.
Quick facts
| Item | Detail | Date | Source |
|---|---|---|---|
| Flood events, Charleston Harbor | 0 in 1925; 75 in 2023, counted at the 7.0 ft MLLW minor-flood threshold | NWS database | NWS Charleston |
| Design contract | US$150 million joint venture contract for design of coastal storm risk infrastructure | July 30, 2026 | Stantec release |
| Total program value | US$1.2 billion | July 30, 2026 | Stantec release |
| Federal cost share | 65 percent | August 4, 2026 | Army.mil |
| Status | “currently in the preconstruction and design phase” | August 4, 2026 | Army.mil |
| Early construction | Early phases slated for 2027 to 2031, pending funding | August 4, 2026 | Army.mil |
| Low Battery seawall | $71 million, nearly 5,000 feet of the historic battery | February 18, 2026 | City of Charleston |
Background
The National Weather Service’s database uses verified hourly water levels from 1921 through 1979 for its early years. It counts an event when the water passes 7.0 feet above mean lower low water. On December 17, 2023, the gauge read 9.86 feet, above the major-flood threshold.
The city has already spent on its waterfront. The Low Battery restoration cost $71 million, and the City says it was “paid for mostly by the city’s hospitality tax.” The project strengthened nearly 5,000 feet of the battery and, in the City’s words, reinforces the peninsula against “rising seas, storm surge, and increasingly intense rainfall.”
The larger effort belongs to the Corps’ Charleston District. In July 2026, Stantec and its partners won a US$150 million joint venture contract to design “critical infrastructure supporting coastal storm risk management on the Charleston peninsula.” Stantec says the team will lead the design of more than eight miles of integrated coastal infrastructure along the waterfront. Stantec is working with Johnson, Mirmiran and Thompson (JMT) on the design.
Timeline
- 1925: The gauge records no flood events above the minor-flood threshold.
- December 17, 2023: The gauge reads 9.86 feet MLLW, above the major-flood threshold.
- February 18, 2026: The City celebrates completion of the $71 million Low Battery restoration.
- July 30, 2026: Stantec announces the $150 million design contract, within a US$1.2 billion program.
- August 4, 2026: The Corps says the project is in preconstruction and design, with a phased approach that protects the most vulnerable areas first. Early phases are slated for 2027 to 2031, pending funding.
What it means for property managers and agents
The timing is the part to watch. The Corps ties early construction to 2027 through 2031, and it says that depends on funding. Until funding is settled, a manager should treat the waterfront work as a plan with dates attached, not a schedule to build around.
The Low Battery is a finished project. Owners and managers with properties near the battery have a completed example to point to when a client asks what the city has already done on the waterfront.
What it means for trades and contractors
The current contract is for design, and construction bids have not been published. For trades, the practical step is to watch the Corps’ Charleston District for the first construction solicitation. No bid schedule exists yet, so there is nothing to plan a bid around.
Questions people ask
How big is the project? Stantec cites a total program value of US$1.2 billion. The July 2026 contract covers the design work.
When will construction start? The Corps says early phases are slated for construction between 2027 and 2031, pending funding.
How much of the cost is federal? The Corps reports a 65 percent federal cost share.
Has the harbor flooded more often? The NWS database counts 0 flood events above the minor-flood threshold at Charleston Harbor in 1925, and 75 in 2023.
Sources
- NWS Charleston, Coastal Flood Event Database, Charleston Harbor table (1921 to 1979 record note; 1925 and 2023 rows): weather.gov/chs/coastalflood
- Stantec, “Stantec joint venture selected by U.S. Army Corps of Engineers to advance coastal resilience on Charleston’s peninsula,” July 30, 2026: GlobeNewswire
- U.S. Army Corps of Engineers via Army.mil, “Charleston, SC, flood concerns are high priority for the Corps of Engineers,” August 4, 2026: army.mil
- City of Charleston, “City of Charleston celebrates completion of Low Battery restoration,” February 18, 2026: charleston-sc.gov
Last updated October 7, 2026.