Port trucks headed for the Wando Welch terminal and commuters share the Long Point Road interchange on I-526. SCDOT has put $325 million into rebuilding it. A contractor’s August 2026 release describes a project of about $227 million, and the sources do not explain the difference.

Quick facts

ItemDetailDateSource
Total project cost$325 millionOctober 21, 2024SCDOT release
Federal grant$195 million from USDOT, plus $65 million in federal dollars already apportioned to South CarolinaOctober 21, 2024SCDOT release
State funds$65 millionOctober 21, 2024SCDOT release
Design-build value“approximately $227 million in total design-build project”August 3, 2026Parsons release
Truck share on Long Point RoadEstimated to fall from 70% to 15% with the preferred alternativeProject FAQ, undatedSCDOT project FAQ
Construction startAnticipated in 2027, lasting about three and a half yearsProject FAQ, undatedSCDOT project FAQ

Background

SCDOT’s project page describes a problem that is easy to picture. Heavy commuter traffic and large trucks use the interchange to reach the Wando Welch Port terminal, and planning studies identified a need for operational improvements at mile point 28 on I-526.

The money came in October 2024. SCDOT announced a $195 million federal grant from the U.S. Department of Transportation, and said the total cost is $325 million. The funding package also includes $65 million in federal dollars already apportioned to the state and $65 million in state funds.

The next steps were slower. SCDOT’s project FAQ says the design-build selection began in fall 2025. On June 22, 2026, SCDOT posted a notice of award, and on August 7 it posted an executed agreement. Ames Construction is part of the design-build team. In its August 3 release, Parsons said it would serve as lead designer, and described “approximately $227 million in total design-build project.”

That is the open question. A $325 million total in 2024 and a roughly $227 million design-build project in 2026 might describe the same work, or different scopes. The sources reviewed do not say which.

Timeline

  • October 21, 2024: SCDOT announces the $195 million federal grant and a $325 million total project cost.
  • Fall 2025: The design-build selection process begins, per the project FAQ.
  • June 22, 2026: SCDOT posts a notice of award.
  • August 3, 2026: Parsons announces its role as lead designer with Ames Construction, citing about $227 million for the design-build project.
  • August 7, 2026: SCDOT posts an executed agreement.
  • 2027: Construction is anticipated to start, per the project FAQ, and to last about three and a half years.

What it means for relocating businesses

The truck numbers are the real signal here. If SCDOT’s estimate holds, Long Point Road itself goes from a road that’s 70 percent trucks to one that’s mostly cars, while the new ramps take on almost all the truck traffic instead. For a business weighing a site near the interchange, that’s the difference between a street built around passenger access and one still built around freight. The estimate is unmeasured, so treat it as a planning assumption, not a guarantee, when you compare a Long Point Road address to one elsewhere in the port corridor.

The cost gap is the other thing worth watching before committing to a timeline. SCDOT’s $325 million figure is two years older than Parsons’ $227 million design-build number, and nothing in the record says why they differ. If the project has narrowed in scope since 2024, that could also mean a narrower construction footprint and a shorter disruption window than the original plan implied. Ask SCDOT directly which figure describes the work still planned before you build a 2027 opening around it.

Questions people ask

What does the interchange project cost? SCDOT’s October 2024 release gives $325 million, funded by a $195 million federal grant, $65 million in other federal dollars, and $65 million in state funds.

Why does a 2026 release show $227 million? The Parsons release describes “approximately $227 million in total design-build project.” It does not say how that figure relates to SCDOT’s $325 million total.

When will construction start? The project FAQ anticipates construction in 2027 and says it would last about three and a half years. The 2026 releases do not give a start date.

Who is designing it? Parsons is the lead designer on the Ames Construction design-build team, selected in 2026 according to its August 3 release.

Sources

Last updated October 7, 2026.