In October 2020, Charleston City Council approved a plan to turn 196 acres on the upper peninsula into homes, parks, and shops. Six years on, the plan is still on paper. In late 2025 the island held nothing but grass and shrubs, and the City had no submittal for it.
Quick facts
| Item | Detail | Date | Source |
|---|---|---|---|
| Site | Approximately 196.1 acres, rezoned to Planned Unit Development (PUD) | Aug 19, 2020 | City of Charleston Planning Commission agenda |
| Planning Commission | “RECOMMEND APPROVAL WITH CONDITIONS (7-0)” | Aug 19, 2020 | City of Charleston Planning Commission agenda |
| Council approval | Passed second and third reading; ratified as Ordinance 2020-144 | Oct 27, 2020 | City of Charleston City Council minutes |
| Planned homes | “could sprout 4,260 new homes, along with parks and commercial space” | Nov 30, 2025 | Post and Courier |
| Affordable housing | “20% of over 4,000 apartments and condos would initially be considered affordable” (developer’s figures) | Oct 27, 2020 | ABC News 4 |
| Status | “Really, nothing has been submitted to the city with regards to moving forward with Laurel Island proper” | Nov 30, 2025 | Post and Courier |
| Vesting extension | City Council approved a one-year extension of the vesting period | Jan 13, 2026 | City of Charleston City Council minutes |
Background
The island was a garbage landfill on the waterfront before it was a development plan. Over the years it has been pitched as a new port, a rail yard, and a resort community.
The 2020 version was the one that passed. In August the Planning Commission voted 7-0 to recommend approval with conditions. At the October hearing, Historic Charleston Foundation asked for a fuller management plan for the Robert Mills and Standard Oil ruins, which still sit on the property. Council gave final approval on October 27, 2020. ABC News 4 called the vote unanimous.
The City’s 2021 contract expected buildings to rise by early 2024. That date came and went, and the island is still waiting.
Timeline
- August 19, 2020: The Planning Commission recommends approval with conditions, 7-0.
- October 27, 2020: Council passes the PUD on second and third reading. It is ratified as Ordinance 2020-144.
- 2021: The City signs a plan and development contract that expects construction by early 2024.
- Early 2024: The construction date passes.
- Late 2025: The island still holds nothing but grass and shrubs.
- November 30, 2025: Josh Martin, a planning official and special assistant to the mayor, tells the Post and Courier that nothing has been submitted for the site.
- January 13, 2026: Council votes unanimously to extend the PUD’s vesting period by one year. The minutes do not describe construction.
What it means for property managers and agents
The approval is real, and so is the extension. What’s missing is a plan that anyone has filed. Any movement would appear first on the Planning Commission and City Council agendas, posted on the City’s Agenda Center. The Post and Courier counts Laurel Island among four large redevelopments on the peninsula, but for now it is a calendar item to watch, not a supply of units to plan around.
The affordable housing terms reward a close read. In 2020, the developer’s figures put 20 percent of the homes in the affordable category. The October 2020 minutes show how the split would work. Ten percent would be kept affordable permanently, and another 10 percent for ten years. A councilwoman asked that the ten-year clock start at each unit’s first lease. Whether the filed plan still reads that way is a question for the City’s current records.
Questions people ask
Has Charleston approved a plan for Laurel Island? Yes. City Council approved the planned unit development on October 27, 2020, and the bill was ratified as Ordinance 2020-144.
How many homes are planned? The Post and Courier reports that the approved plans could bring up to 4,260 new homes. That is the approved framework, not a current proposal.
Has construction started? No source reports construction. As of November 30, 2025, the island held nothing but grass and shrubs. The January 2026 vesting extension does not describe any construction.
Who owns the land? The October 27, 2020 Council minutes list the property as owned by Charleston County and LRA Promenade North LLC. Post and Courier coverage from 2025 identifies a local real estate professional who represents Lubert Adler in the project.
What affordable housing is planned? ABC News 4 reported the developer’s figures: 20% of over 4,000 apartments and condos would initially be considered affordable.
Sources
- City of Charleston, Planning Commission agenda, August 19, 2020: Laurel Island PUD rezoning, approx. 196.1 ac
- City of Charleston, City Council minutes, October 27, 2020: Regular Meeting minutes
- City of Charleston, City Council minutes, January 13, 2026: Regular Meeting minutes
- ABC News 4, October 27, 2020: City Council unanimously approves Laurel Island development
- Post and Courier, November 30, 2025: Many thousands of new homes and a big population rebound planned on Charleston peninsula