The SC Ports Authority promised a new rail yard on the former Navy Base by July 2025. By October 2025, it was about 80 percent built, “over budget and behind schedule,” and still had no opening date. The project is costing at least $550 million in taxpayer money, and the Ports Authority is negotiating in private with the two railroads it needs to use the yard.
Quick facts
| Detail | Fact | Source |
|---|---|---|
| Site | 118 acres near the Leatherman Terminal, North Charleston | SC Ports Authority |
| Cost | At least $550 million | SC Daily Gazette, Feb 24, 2026 |
| Cranes | Six electric rail-mounted gantry cranes | SC Ports Authority, Oct 2024 |
| Rail capacity | 1 million rail lifts a year | SC Ports Authority, Oct 2024 |
| Railroads | CSX and Norfolk Southern | SC Ports Authority |
| Status | About 80% built, no opening date | Post and Courier, Oct 17, 2025 |
Background
A 2024 Ports Authority release described six gantry cranes, service by CSX and Norfolk Southern, and an opening in July 2025. That date slipped. By October 2025, the Post and Courier reported the yard would not open in January as previously scheduled, calling it “over budget and behind schedule.” In February 2026, the SC Daily Gazette reported that the project’s head, Micah Mallace, told state lawmakers the rail yard was costing taxpayers at least $550 million, but could not share the latest news because it involved confidential negotiations with the railroads.
Those negotiations are the real obstacle. Both CSX and Norfolk Southern have their own facilities in North Charleston and have been reluctant to use the new yard. Norfolk Southern has said it will not use it unless the Ports Authority also spends $27 million on unrelated rail improvements that benefit the railroad.
Timeline
- February 2024: The Ports Authority announces a July 2025 opening.
- October 2024: The authority cites $400 million in state funding and 1 million rail lifts a year of capacity.
- October 2025: The yard is about 80 percent built. No new opening date is given.
- February 2026: State lawmakers learn the project costs at least $550 million, with railroad negotiations still unresolved.
What it means for trades and relocating businesses
Nothing here gives a date to plan around. Norfolk Southern’s access depends on a separate track project, the Southern Connector, which had no contractor as of October 2025. Before bidding on rail-connection work, confirm which contracts have actually been awarded.
Questions people ask
Is the Navy Base rail yard open? No. As of October 2025, it was about 80 percent built, with no new opening date.
How much does the project cost? At least $550 million, according to state lawmakers’ briefing in February 2026.
Which railroads will use it? CSX and Norfolk Southern are named, but Norfolk Southern says it won’t use the yard unless the Ports Authority pays for $27 million in unrelated improvements.
Sources
- SC Ports Authority, Navy Base Intermodal Facility page: scspa.com
- SC Ports Authority, October 16, 2024: scspa.com
- SC Daily Gazette, “SC Ports gives private update on public rail yard project,” February 24, 2026: scdailygazette.com
- Post and Courier, October 17, 2025: postandcourier.com