In April 2025, the state announced a $2.8 billion high-performance computing center at 4000 South Pine Street in Spartanburg, with at least 27 new jobs. A year later, the company had asked to multiply its power generation there, and neighbors had gone to court. Initial operations were targeted for the third quarter of 2026. No source checked shows that they have started.
Quick facts
| Item | Detail | Date | Source |
|---|---|---|---|
| Investment | $2.8 billion | April 21, 2025 | SC Commerce |
| Jobs | At least 27 new jobs | April 21, 2025 | SC Commerce |
| Location | 4000 South Pine Street, Spartanburg | April 21, 2025 | SC Commerce |
| Permitted generators | 24 natural gas generators, already permitted | April 22, 2026 | Post and Courier |
| Power request | More than 450 megawatts | April 22, 2026 | Post and Courier |
| Lawsuit | Southern Environmental Law Center suit against the county and Valara, filed July 2026 | September 2026 | Post and Courier |
Background
NorthMark is a multi-strategy investment firm. It provides strategic advice, asset management, and value-added services to privately owned companies around the world. Spartanburg will be its fifth U.S. operation and its first in South Carolina.
The state’s announcement described a high-performance computing center designed to support a portfolio of businesses. It also said the company expects to use regional businesses and suppliers for regular maintenance and operations support.
The power is where the project got complicated. According to the Post and Courier, the facility was already permitted for 24 natural gas generators. In April 2026, the company asked to increase its power generation to more than 450 megawatts. Residents who live next to the site brought the Southern Environmental Law Center into the fight. The center sued Spartanburg County and Valara, the company’s data center subsidiary, in July 2026. In September, a court heard arguments on an injunction in a Spartanburg courtroom. The county and Valara had already filed motions to dismiss the case. The Post and Courier reported that the gas generators would total 457 megawatts. The site is a 300-acre parcel, and the data center is already under construction on South Pine Street. The same environmental group had previously fought for stricter enforcement of air pollution limits under the facility’s original permit. The new application proposes a catalytic reduction control device to reduce pollutants, and the SELC has said that is not enough.
Timeline
- April 21, 2025: The state announces the $2.8 billion computing center and at least 27 jobs.
- April 22, 2026: The Post and Courier reports the request to increase power generation to more than 450 megawatts.
- July 2026: The Southern Environmental Law Center sues Spartanburg County and Valara on behalf of residents.
- September 2026: The court hears the injunction request. No ruling appears in the report.
- Third quarter of 2026: Initial operations are targeted. No source checked confirms a start.
What it means for relocating businesses
Treat this as a 2025 announcement with a 2026 target. The public record shows a commitment of at least 27 jobs, later phases with no published details, and a request for much more power than the original permit covered. The lawsuit and the pending request mean the project’s timing and scale are still open. The one operating detail the state gives is that the company expects to use regional businesses and suppliers for regular maintenance and operations support, which makes local vendors the part of this project a business can plan for now.
Before you use this project in a site decision, check the current status with Spartanburg County and the state, and check the permit record.
Questions people ask
Where is the NorthMark project? At 4000 South Pine Street in Spartanburg.
How many jobs will it create? The state says at least 27 new jobs.
When does it open? Initial operations were targeted for the third quarter of 2026. No published source confirms a start date.
Has the power increase been approved? No decision on the request has been published. In September 2026, the Post and Courier reported a lawsuit and an injunction hearing. No ruling is reported.
Sources
- SC Commerce, April 21, 2025: NorthMark Strategies selects Spartanburg County to establish first South Carolina operation
- Post and Courier, April 22, 2026: Spartanburg data center that got tax breaks wants 400 megawatt energy production increase
- Post and Courier, September 2026: Environmental group faces off with Spartanburg County during injunction argument
Last updated October 7, 2026.