USC broke ground on its Health Sciences campus in the BullStreet District in February 2025. By August 2026, the monumental staircase was in, interior framing was complete, and the university said the $300 million building remained on schedule for completion before the fall 2027 semester.
Quick facts
| Item | Detail | Date | Source |
|---|---|---|---|
| Site | 16 acres in the BullStreet District, Columbia | February 21, 2025 | USC |
| Investment | $300 million | February 21, 2025 | USC |
| Facility size | More than 300,000 square feet | February 21, 2025 | USC |
| Construction status | Interior framing complete; staircase installed; work continues on mechanical systems, masonry, and glazing | August 2026 | USC |
| Expected completion | Before the fall 2027 semester | August 2026 | USC |
Background
USC selected Gilbane to lead the planning, design, development, construction, and operations of the campus, and held a groundbreaking for the School of Medicine Columbia building in February 2025. By August 2026, the university’s own update described real progress: interior framing complete, the monumental staircase installed, and work underway on mechanical systems, masonry, and exterior glazing. The same update said planning was advancing for a future STEM Building on the campus, with construction expected to begin in spring 2027.
Timeline
- February 21, 2025: USC breaks ground on the Health Sciences campus.
- August 2026: USC reports interior framing complete and the staircase installed, with the project on schedule.
- Fall 2027: Expected completion.
- Spring 2027 (planned): Construction expected to begin on a future STEM Building on the same campus.
What it means for relocating businesses
Two different timelines exist on this one campus. The Health Sciences building has interior framing complete and its staircase installed, with a fall 2027 target that now has visible work behind it. The planned STEM Building next to it hasn’t started; construction is only expected to begin in spring 2027. A health care, research, or lab-services business weighing a move should ask USC which phase it’s actually planning around, since “the BullStreet health campus” covers one building that’s nearly finished and a second that’s barely begun.
Questions people ask
What is the USC project? A $300 million Health Sciences campus in the BullStreet District, anchored by a medical education and research facility for the School of Medicine Columbia.
When is it expected to be finished? Before the fall 2027 semester, per USC’s August 2026 update.
Is the campus finished? No. As of August 2026, interior framing was complete and work continued on mechanical systems, masonry, and glazing.
What else is planned nearby? USC says it is planning a future STEM Building on the same campus, with construction expected to begin in spring 2027.
Sources
- USC, February 21, 2025: School of Medicine Columbia groundbreaking, Health Sciences Campus at BullStreet District
- USC, August 2026: What you missed this summer: Facilities
- Gilbane, January 23, 2023: Gilbane Selected to Lead Planning, Design, Development, Construction and Operations of University of South Carolina’s Health Sciences Campus
Last updated October 7, 2026.

