Charleston Growth: Verified Facts
Current figures, project status, and source links for the Charleston growth pages. Updated October 27, 2026. Figures below distinguish company announcements, public project costs, land transactions, zoning capacity, and economic impact.
Union Pier
Figure: A 70-acre waterfront site
Status: Under contract for sale to Marti Holdings; the site is in the City’s zoning approval process. The sale price is not presented as a redevelopment investment.
Source: SC Ports Authority
Laurel Island
Figure: A mixed-use planned unit development; detailed unit, retail, and office figures are omitted because the project file contains the submitted PUD, not the signed ordinance.
Status: City Council approved the PUD in October 2020. Reviewed records show no construction schedule. A January 2026 Council record confirms the PUD and a vesting-period extension.
Source: City of Charleston Council minutes
Boeing 787 expansion
Figure: More than $1 billion and 1,000+ planned jobs over five years
Status: Boeing broke ground in November 2025. The final assembly building size is omitted: Boeing’s 2025 and March 2026 materials give conflicting size descriptions, and the project review says not to use either pending clarification.
Source: Boeing, Nov. 7, 2025; Boeing, Mar. 23, 2026; March 2026 building update
Google data centers
Figure: $9 billion announced through 2027 in October 2025; a September 2024 release had announced $3.3 billion for expansion of the Berkeley campus and construction of two Dorchester campuses
Status: Both announcements describe the same Berkeley and Dorchester sites. The releases do not say whether the $9 billion includes or is additional to the 2024 project figure, so this page does not add the announcements together.
Source: Google, Oct. 13, 2025; South Carolina Governor’s Office, Sept. 26, 2024; 2024 announcement
Redwood Materials
Figure: $3.5 billion announced investment; 1,500 jobs planned
Status: Announced for Camp Hall in Berkeley County in 2022. These are the announced project figures, not a current estimate of spend to date.
Source: South Carolina Governor’s Office, Dec. 14, 2022
Lowcountry Rapid Transit
Figure: $625.10 million total capital cost; 21.3 miles; 20 stations
Status: The April 2026 FTA profile lists revenue service in late 2030. The project’s 2026 schedule shows construction beginning in 2027 and testing after substantial completion in fall 2029; 2029 is not the stated rider-service date.
Source: Federal Transit Administration, April 2026 profile; Lowcountry Rapid Transit project schedule; 2026 project schedule
I-526 / Long Point Road interchange
Figure: SCDOT’s 2024 total project cost: $325 million. Parsons’ 2026 release describes an approximately $227 million design-build project; the sources do not reconcile the scopes.
Status: The $325 million package was described as fully funded: $195 million federal grant, $65 million other federal funds, and $65 million state funds. SCDOT posted the award in June and executed agreement in August 2026; notice to proceed remains TBD, with substantial completion due August 2030.
Source: SCDOT grant announcement and project page; Parsons Aug. 3, 2026 release; SCDOT award and contract status; Parsons design-build value
Navy Base Intermodal Facility
Figure: At least $550 million was reported in February 2026; a 2026 PBS interviewer later cited about $690 million, which the SC Ports president did not explicitly confirm
Status: SC Ports says construction is nearly complete while southern rail access design continues. A $545 million project budget was reported in June 2025. The $550 million was originally appropriated for the rail yard and a separate barge project; the June 2025 report said it was redirected to the rail yard. No newer official budget figure was found.
Source: SC Daily Gazette, Feb. 24, 2026; SC Ports project status; PBS interview transcript; SC Ports current project status; 2026 interview transcript
Charleston Peninsula flood protection
Figure: USACE’s feasibility study gives a $1.1 billion estimate (about $1.132 billion in its 2022 price-level table); Stantec’s July 2026 release describes a $1.2 billion total program value and a separate $150 million design contract.
Status: In preconstruction engineering and design; construction funding for the full project is not secured. These $1.1B and $1.2B figures use different descriptions and bases; the sources do not establish that one supersedes the other. The completed $71 million Low Battery seawall is separate.
Source: U.S. Army Corps of Engineers, feasibility study; Stantec / USACE, July 30, 2026; City of Charleston; 2026 program value and design contract; City Low Battery update
Camp Hall rail
Figure: $190 million; approximately 25 miles
Status: Construction remains ongoing. The project’s construction page says work is anticipated to continue through fall 2026; an April 2026 progress percentage is not treated as current completion.
Source: Palmetto Railways / Camp Hall Rail
Costco at Ingleside / Blue House Road
Figure: A possible North Charleston warehouse has been reported based on a land transaction and a site-plan filing.
Status: Costco had not publicly confirmed the location or announced an opening date as of October 21, 2026. No total store construction cost or job count was published. The land price and site dimensions are omitted because the primary deed and SCDES plan were not linked in the reviewed materials.
Source: Charleston Business Report, reporting recorded land transaction and SCDES filing
Novant Health
Figure: No public construction-cost figure located for the Charleston-area projects
Status: The Clements Ferry freestanding emergency department opened July 28, 2026. Novant’s separate $2.4 billion figure was for acquiring three hospitals across coastal South Carolina, including facilities in Mount Pleasant, Hilton Head, and Hardeeville; it is not a new Charleston-only project budget.
Source: Novant Health: Clements Ferry opening; 2024 acquisition announcement
Charleston Harbor depth
Figure: 52 feet; the deepest harbor on the U.S. East Coast
Status: Completed in December 2022.
Source: SC Ports Authority
Charleston metro population
Figure: 889,263; forecast to reach one million by 2032
Status: CRDA regional figure and forecast; the metro spans Berkeley, Charleston, and Dorchester counties.
Source: Charleston Regional Development Alliance
SC Ports economic impact
Figure: $87 billion annual statewide economic impact; 260,000 jobs supported
Status: 2023 study estimate. Economic impact is not capital investment and is not included in project-cost totals.
Source: SC Ports Authority, 2023 Economic Impact Study
Why there is no single investment total
The figures above do not share one accounting basis. Company announcements describe planned investment; public works list project costs; Costco’s site purchase is separate from an unpublished store budget; Laurel Island’s detailed zoning figures are withheld pending the signed ordinance; and SC Ports’ $87 billion is annual statewide economic impact. Adding them together would produce a misleading headline.
The previous $10.9 billion and $16–17 billion headlines are not repeated here. The underlying announcements include overlapping Google site scopes, public project budgets, private investment commitments, property transactions, and annual economic impact. The source record does not support a single, consistently scoped total without assumptions about overlap and project scope.